The main challenge in the existing protection system is the long coordination time
interval between the downstream and upstream relay and the lack of communications
between the protective devices that results in cascading failure. the existing protection
and control system was reviewed and upgraded to Make sure the interlocking between
the chiller and lubrication pump motor. In addition the following countermeasures
also can be considered to improve design vulnerability of the existing protection
system;
⓵ Quick detection of the temperature rise before insulation failure using IEC 61850
with smart sensors.
⓶ Logical Interlocking by implementation of IEC61850 substation automation protocol.
⓷ Apply breaker failure protection scheme using digital relays based IEC61850.
Recently constructed NPPs applied digital relays and existing NPPs also getting retrofit
the analog relay with digital relays so, peer to peer communication between relays
can be applied without additional equipment installations and make it possible to
apply above mentioned solutions.
3.1 Existing Electrical Protection and Control System
The current protection coordination for the central chiller motor pump is achieved
using time over current relay (51) for incoming feeders, and instantaneous time overcurrent
relay (50) and time overcurrent relay (51) for branch feeders. The coordination time
interval (CTI) between the downstream and the upstream protection devices has to be
considered and followed According to IEEE, the CTI between downstream and upstream
protection devices, should be about 200~250 ms. This CTI cause late trip of the upstream
circuit breaker when the circuit breaker of downstream relay fails to trip[4][5]. The existing fault clearing time by the circuit breaker of the upstream feeder relay
in case of failure of the CB of the downstream relay can be calculated as shown in
Table 1;
Table 1. Fault clearing time by circuit breaker.
Action
|
Clearing time
|
Downstream relay trip time
|
40 ms
|
Lockout relay operation
|
8 ms
|
Five cycle CB
|
83 ms
|
CTI between downstream and
upstream relay
|
250 ms
|
Total time
|
381 ms
|
As shown in Fig. 5 when a fault occurs in the motor feeder circuit it would take 131 ms for the CB of
the downstream relay (50) up to 381 ms of the CB of the upstream relay to pick up
and clear the fault, that means in case of downstream CB failure to trip, the fault
occurred in the motor continued about 381 ms until the upstream CB pickup and remove
the fault, resulted in release of substantial thermal energy during short circuit
fault causing thermal overheating of the motor stator windings.
Fig. 5. Fault clearing time curve
The existing relay coordination curve between downstream and upstream circuit breakers
for the central chiller water pump motor circuit of Hanbit NPP unit (2) was shown
in Fig. 6.
In the following paragraphs, there is going to be much more explanation about improvement
of the existing electrical protection system to prevent cascading failure in NPP’s
electrical protection power system.
3.3 Prevention of Cascading Failure Using IEC61850
IEC 61850 is a communication protocol that can give many benefits to the NPP electric
power system, not only cost savings but also design improvement. However, in the MV
system of NPPs, electrical system protection is relying on the time-current curve
(TCC) coordination in the case of overcurrent fault. Using IEC61850 can significantly
reduce communication time, which is critical when the fault occurs. IEC 61850 provides
fast communication by using designated communication types; MMS, GOOSE and SV [6]. GOOSE is the fastest message among the three types of IEC 61850 communication types
by using 2 OSI layers only. GOOSE message is especially for the urgent actions like
trip, interlocking signals. On the other hand, Korean NPPs have applied digital relays
since Shin-Kori 3&4 nuclear power plant. The digital relay is intelligent electronic
device and it supports IEC 61850 communication functions. So, communication between
IEDs with IEC 61850 is applicable on the MV system without additional device installation
[7].
3.3.1 Communication-Based Breaker Failure Protection
The IEC61850 based GOOSE scheme allows continuous communication between IEDs, once
the overcurrent relay detects a fault, it initiates a direct transfer trip (DTT) signal
to the upstream circuit breaker to clear the fault [8]. DTT needs to be dependable during fault conditions to allow the trip signal to be
received correctly. This type of peer to peer communications based breaker failure
protection can be applied in different ways:
• As a function in IEDs that initiates the breaker failure protection when it receives
the trip signal from the relay protecting the faulted power system equipment.
• As a built-in function in the protective IED that detected the fault and issued
the trip signal.
3.3.2 Implementation of Circuit Breaker Failure in IEC 61850 environment
Fig. 7 shows the data communication between relays using IEC61850 environment, when a fault
occurs in the downstream feeder. The downstream relay will detect a fault and will
issue a tripping GOOSE message to clear the fault. The CBF function will respond to
these GOOSE message and the breaker failure timer will start. In case of breaker failure,
the breaker failure function will point out this failure and a GOOSE message will
be sent over the LAN network to trip upstream breakers and initiate DTT to the upstream
relay to clear the fault. When the IED initiates a trip signal, it starts a timer
and monitoring the CB current. If the current does not go away in a predefined time,
the IED issues a re-trip or trips the upstream breakers to isolate the faulted one.
After the downstream relay gets a tripping signal but doesn’t received tripping signal
from the breaker, the downstream relay shall send a breaker failure initiate signal
(BFI) through a GOOSE message to the upstream relay to force it to trip the upstream
circuit breaker, nevertheless the blocking timer has expired or not [9].
Fig. 7. Data communication between relays
In order to achieve this kind of communication, IEC61850 defines specific protective
features as (LN), a specific category of specified attributes to each logical node
are also defined. LN can also be currently located in different types of IEDs. Calculations
of voltage, current and condition are transmitted to the relays via a process bus
that is an ethernet channel of communication. The RBRF class is confined to circuit
breaker failure (CBF) protection as per IEC61850-7-4, see Table 2. The IEC61850 standard documents define the attributes, (OpIn) corresponds to re-trip
order from the RBRF to the broken CB (stage I or inner trip), (OpEx) corresponds to
the corresponding breaker tripping command (stage II or external trip), And FailMod
deals with the assessment of breaker malfunction by current status, This LN's specifications
are described in IEC 61850 part 5.
Table 2. Class assigned to CBF
Attribute
|
Discription
|
class
|
Class
|
RBRF
|
OpCntRs
|
Operation re-set counter
|
Details about the condition
|
Str
|
ACD
|
Start, timer running
|
OpEx
|
ACT
|
BF trip (“External trip”)
|
OpIn
|
ACT
|
BF trip (“Internal trip”)
|
Settings
|
StrVal
|
ASG
|
Start Value
|
FailMod
|
ING
|
BF Mode detection.
|
FailTmms
|
ING
|
BF Time Delay for downstream trip.
|
ReTrMod
|
ING
|
Retrip Mode.
|
In case of fault, LN transfer a message to the RBRF (initiated by the CBF), and the
RBRF triggers the timer. The RBRF gives a message via the network to the XCBRs (logical
node for circuit breaker) to trip the upstream CB if the downstream breaker fails
to trip / clear the fault. All upstream XCBR register to and receive this message
at the same time to implement next required actions. The RBRF information communication
with other logical nodes is shown in Figure 8. Blocks IHMI, CALH, ITCI, RBRF, XCBR
and Pxyz are logical nodes ((Pxyz stands for the main protection (e.g., PIOC for instantaneous
overcurrent)); Table 3 gives functional descriptions of each logical nodes.
Table 3. Functional descriptions of logical nodes
Logical Nodes
|
Functional Descriptions
|
IHMI
|
Human Machine Interface
|
CALH
|
Fault indication and Alarm signal
|
ITCI
|
Tele-controlling application
|
RBRF
|
Breaker failure
|
XCBR
|
Circuit Breaker
|
PIOC
|
Instantaneous overcurrent protection
|
PTOC
|
Time overcurrent protection
|
The RBRF receives from the protection LNs a trigger signal. The RBRF transmits four
kinds of signals:
• Data about the fault is transmitted via IHMI and ITCI.
• trip indication transmitted through IHMI, ITCI and CALH.
• Settings are sent to IHMI and ITCI.
• All subscribed breakers (XCBR) receive Trip Commands through PIOC, PTOC and a coordination
signal was published through CILO signal.
The first three classes of signals were transmitted to upstream logical nodes, which
are indicators to monitor and record bay-level events. The last signals are defensive
and the most important.as reliable communication links between the RBRF and the XCBRs
subscribed are highly essential [10].
Fig. 8. Data Communication between RBRF and other logical nodes
3.3.3 IEC61850 based zone selective interlocking
ZSI is based on currents comparison between protective zones. It has a communication
control logic system between downstream and upstream breakers. The IEC61850 GOOSE
based ZSI scheme always concern about blocking time. It is used to improve the level
of protection in the electrical protection power system, through communication between
protective relays across the protected zones to reduce the fault clearing time. During
ground fault or phase fault conditions the protective devices electronic interlocking
allows the devices close to the fault to override its preset time delay automatically
and clear the fault without intentional time delay [11]. As illustrated in Fig. 9, when a short circuit fault occurs at the central chiller motor, both the faulted
downstream relay and the upstream relay detect the fault. In order to block tripping
the main breaker (NB-S02-01) and avoid loss of power for the whole bus, the faulted
downstream relay of the CB (NB-S02-18) sends a blocking signal to block the upstream
relay from tripping the upstream main CB (NB-S02-01) and averting the whole bus power
losses. After fault clearance, fault is not detected any more, but if a fault is not
cleared and both the downstream feeder relay and upstream relay still detecting the
fault, the main upstream relay will trip the main CB (NB-S02-01) as a backup protection.
Fig. 9. Protection coordination scheme using ZSI
The result is that other devices remain unaffected by the fault and the fault is cleared
more rapidly than the existing protection system without using ZSI. The main advantage
of applying IEC61850 based ZSI is to reduce blocking time between the downstream and
upstream relay to its minimum without affecting relays operations. Accordingly, we
need to consider the opening time and communication time between the downstream CB
(NB-S02-18) and the upstream CB (NB-S02-01) that requires extended blocking time to
give the feeder breakers a time to operate first and isolate the fault. For majority
of the relays the internal rationale execution time from overcurrent relays to pick
up the fault till the time to send a GOOSE messaging within 2 ms up to 10ms based
on network traffics, it is also the same from receiving a GOOSE to trip the upstream
breaker. The relay contact responding time is about 8 ms. If we consider medium voltage
five-cycle circuit breaker that would add additional (83ms) for 60Hz system. Depending
on network configuration and design, the overall travelling time among the downstream
relay and the main upstream relay depending on the distance between the relays and
the Ethernet network would be about 20 ms [12]. So, the fault clearing time between the downstream and upstream feeder relays using
ZSI can be calculated as shown in Table 4;
Table 4. Fault clearing time using IEC61850 based ZSI
Action
|
Clearing time
|
Downstream relay trip time
|
40 ms
|
Lockout relay operation
|
8 ms
|
Five cycle CB
|
83 ms
|
Communication signal travelling time between downstream and upstream relay
|
20 ms
|
Total time
|
151 ms
|
As a result, by applying IEC61850 based ZSI, the fault clearing time of the upstream
CB would be 151 ms for five cycle CB. This time is quite greatly faster compared to
the existing protection time 381 ms which results in decreasing the motor thermal
overheating caused by short circuit fault current.